Remodel update - 12/02/13

Recently completed

  • Receiving area addition walls on Jenifer St. side of property.

Construction work this week (12/02–12/08)

  • Pouring concrete foundation wall on Jenifer St. side of property.
  • Pouring concrete footings in front of the store and, later in the week, pour the foundation walls here.
  • Surface prep on walls in entryway.

What may affect you this week (12/02–12/08)

  • No changes to the retail floor will be made this week.
  • Selective demolition of brick areas wherever new walls are being tied into existing walls. Will be noisy at times.
  • Nonprofit/organizational brochures and flyers in entryway will removed until renovation of foyer is complete.

Coming up in next few weeks

  • No changes to the retail floor in next few weeks.
  • Cart room being rearranged; our foyer will temporarily become smaller.
  • Will be starting on the masonry for the receiving area addition on the Jenifer St. side.