Remodel Update - 5/12

What may affect you this week (5/12–5/18)

  • Will set up construction area for the new Juice/Coffee Bar.
  • Produce reopens (temporarily).
  • Will remove the construction area dividing the registers.
  • Roof work going on, requiring some construction vehicles to park in the lot.
  • Bricklaying starts on the new facade.


On the horizon

  • We will likely be closing the Produce department for floor work in later May. We will still have significant produce offerings available.
  • Work begins on the dock enclosure; little to no impact on customers expected.
  • Construction on new front end office will start. Traffic patterns will change.