East Remodel content

  • Construction work this week (2/10–2/16)

    Tile work in Deli production and service area, and in new staff restrooms.Install walls for enclosed entryway and finish concrete work.Painting the deck in new receiving area addition....
    Published February 10, 2014
  • Construction work this week (2/3–2/9)

    Tile work for Deli production and service area floor.Install walls for enclosed entryway and finish concrete work.Construction continues on new staff restrooms.

    What may affect...

    Published February 3, 2014
  • Construction work this week (1/27–2/2)

    Trenching (saw-cutting concrete) for plumbing and floor work in Deli.Install steel canopy over the entryway. Concrete work in new entryway.Receiving area and Deli roof work. Begin...
    Published February 3, 2014
  • Construction work this week (1/20–1/26)

    Trenching (saw-cutting concrete) for plumbing and floor work in Deli.Removal of brick from walls in entryway.Pouring floor in new receiving addition; roof work begins.

    What...

    Published January 20, 2014
  • Recently completed

    New receiving addition walls constructed.

    Construction work this week (1/13–1/19)

    Temporary wall separating Deli work space from store put up this week; floor work in Deli.Removal of...
    Published January 13, 2014
  • Recently completed

    Progress slowed due to weather.

    Construction work this week (1/6–1/12)
    Slowed due to weather.

    Removal of brick from walls in entryway.Continued construction on the...
    Published January 6, 2014
  • Recently completed

    Steel installed in receiving area addition.Recycling progress sign posted.East on site offices de-constructed, in preparation for mechanical upgrades for store remodel.

    Construction work this week...

    Published December 30, 2013
  • Recently completed



    Structural evaluation of cracked wall on Jenifer St. side of building.Received our “One Can Plan” Dumpsters for recycling building materials.Masonry walls completed for receiving area addition; tying into...
    Published December 23, 2013
  • Recently completed

    Build temporary interior partition in entryway.Pour walls to define the west side of the new entryway.

    Construction work this week (12/16–12/22)

    Removal of brick from walls in entryway....
    Published December 16, 2013
  • Recently completed

    Pouring concrete foundation wall on Jenifer St. side of property, and concrete footings and foundation walls in front of the store.Nonprofit/organizational brochures and flyers in entryway will removed until...
    Published December 9, 2013